STANDBY BATTERY RACK
ASSEMBLY INSTRUCTIONS
APPLIES TO ALL RDC SERIES RACKS
(READ ALL INSTRUCTIONS PRIOR TO INSTALLATION)
Standard and Earthquake-Protected (EP) Racks:
Earthquake-protected racks are similar to standard racks,
with the exception of additional frame bracing, battery restraints,
and cell spacer elements. The battery rack frames are common for
Standard, EP1 and EP2 series for the one-tier, two-tier, three-tier
and two-step racks with the exception of the three-tier EP2 rack.
The frame for the three-tier EP2 rack is unique. RDC-EP racks are
certied to the International Building Code, 2009 edition.
Conguration:
Racks are available in single or multiple tier/step congurations as
shown in Figure 2. Rack components are supplied loose and must
be assembled and secured on-site in accordance with these C&D
assembly instructions, the drawings included with the rack shipment,
and applicable codes.
Rack Location:
Locate racks in a clean, cool, dry place so the batteries are not affected
by sources of radiant heat, such as sunshine, heating units, radiators,
steam pipes, etc. Variations of more than 5 degrees Fahrenheit (3º C)
between cells may cause the battery to become electrically unbalanced.
Top rows of batteries in multiple-tier congurations tend to operate at
slightly higher temperature than those on lower tiers. Always provide
adequate ceiling clearance for ventilation and maintenance.
Anchoring:
To provide stability and safety, racks must be securely anchored
to the oor. Anchor bolts are to be installed per contractor
specications and in accordance with applicable codes. Do not
attach rack to walls without consulting the appropriate structural
engineer. Mounting holes are provided in the base of each frame.
All frames must be secured to oor using all anchor bolt hole
locations.
Do not install batteries until the rack has been properly
installed, with all bolts tightened to specied torque and
frames anchored to the oor.
Do not use oil or grease as a lubricant for cell installation.
Lubrication is usually not required due to the low friction
interface of the insulating covers. If necessary, a small
amount of water, unscented talcum or Dow Corning III can
be applied to the rail covers to reduce friction.
CAUTION:
Grounding:
Rack grounding provisions are integrated into the base of each
frame. Two through holes are located at the center of the frame’s
bottom cross member and may be used to secure a standard NEMA
lug. These holes are 0.44” in diameter and 1.0” between centers.
The surfaces surrounding the holes have been masked and are free
of powder coat to allow electrical contact. Frame to frame grounding
integrity is accomplished via the lower support rail, attached to each
frame with internal/external “star” washers.
Two Tier Standard Rack Two Tier EP Rack
Figure 1. Standard Vs. EP Rack
Figure 2. Typical Rack Congurations
RS02098
These instructions detail the proper procedure for installing
C&D Standard and EP (Earthquake Protected) battery racks.
The following describes how to locate, assemble, and load
open-frame battery racks for C&D battery mounting applications.
Proper attention to these instructions will help ensure safe,
trouble-free performance.
Standard vs. EP2 Rack
Two Tier Standard Rack Two Tier EP2 Rack
TYPICAL RACK GROUNDING
PROVISION
2-Step
1 Tier 2-Tier 3-Tier
Std & EP1
3-Tier
EP2
RS02098/0114/CD www.cdtechno.com
Vue de la page 0
1 2 3 4 5 6 7 8

Résumé du contenu

Page 1 - ASSEMBLY INSTRUCTIONS

STANDBY BATTERY RACK ASSEMBLY INSTRUCTIONSAPPLIES TO ALL RDC SERIES RACKS (READ ALL INSTRUCTIONS PRIOR TO INSTALLATION)Standard and Earthquake-Protec

Page 2 - Brace to Frame

ASSEMBLY INSTRUCTIONS FOR RDC STANDARD AND EP RACKS1. Material Verication: Battery racks are shipped unassembled with a complete set of related draw

Page 3 - Rack Label Placement

5. Installing Support Rail(s): See Figure 5. Place support rail(s) in location using supplied 3/8” bolt, washer, serrated strut nut and nger tighten

Page 4 - Support Rail Installation

ASSEMBLY INSTRUCTIONS FOR RDC STANDARD AND EP RACKS 7. EP Rack Assembly: Install all back restraint rail(s) and cover(s). See Figure 7 and Detail E f

Page 5 - Corner Bracket Reversed

ASSEMBLY INSTRUCTIONS FOR RDC STANDARD AND EP RACKS9. Front Restraint Rail (EP only): With the batteries in place, slide the front side support rail

Page 6 - FIGURE 11

ASSEMBLY INSTRUCTIONS FOR RDC STANDARD AND EP RACKS11. Tie Rod Assembly: Longer EP racks require a tie rod assembly (see rack assembly drawings for d

Page 7 - FIGURE 14

Back to Back Assembly:Where two rows of racks are required, two rack assemblies may be installed back to back.Frame Location: Locate back to back fram

Page 8 - End to End Installation